01 — Infrastructure & Regulatory Gate

Indonesia's electricity system is planned through the national electricity framework and PLN's RUPTL. The 2025–2034 RUPTL identifies data centers among the sectors driving electricity demand and provides for significant investment in generation, transmission, and grid infrastructure [1]. For transaction underwriting, however, the relevant question is narrower: what power capacity is actually evidenced as available or contractually secured for the target campus?

ASEANPrimer Verification Framework
Power Capacity Standard: Binding PLN documentation vs. Non-binding MoU
Substation Capacity: Grid interconnection evidence
Land Title Documentation: HGB title records supporting the ownership/tenure chain [2]
Evidence State Evaluation
Underwriting Condition Evidence State State
Contracted / secured power capacity IM: 50MW / PLN documentation: 20MW CONFLICT
Phase-2 grid / substation capacity Regional upgrade referenced; reservation not evidenced MISSING
HGB title documentation ATR/BPN title records supporting the chain VERIFIED
Environmental approval AMDAL documentation VERIFIED
UNDERWRITING STATE: CONDITIONAL
REGULATORY EXPOSURE: UNRESOLVED
FINANCIAL EXPOSURE: UNQUANTIFIED
VALUATION: BLOCKED
02 — Evidence Conflict & RFI Generation
Illustrative Data Room Evidence
Information Memorandum (IM):
50MW stated as contracted power
Assumes full buildout valuation
PLN Power Documentation:
20MW evidenced / 30MW referenced in MoU
30MW is not supported by binding PLN allocation evidence in the illustrative data room

The engine does not treat management projections, MoUs, or non-binding indications as secured capacity. Accordingly, the underwriting model does not credit expansion revenue to the unverified 30MW capacity.

Generated RFI #01 — PLN Grid Allocation & Capacity Verification
Evidence required: Executed PLN power supply documentation supporting Phase-2 capacity, and/or formal documentation evidencing the relevant substation/grid capacity reservation.
03 — Financial Underwriting
Underwriting Output State
Documented power capacity20MW BASELINE
Expansion capacityBLOCKED
Expansion revenueNOT CREDITED
Incremental infrastructure CAPEXUNQUANTIFIED
Valuation impactBLOCKED
SPA allocationPENDING
Human expert review required before underwriting the Phase-2 expansion.

Traditional due diligence treats power supply as an operational detail. AseanPrimer enforces a traceable sequence: Condition → Evidence → Conflict → RFI → Financial Status → SPA Status. No expansion revenue or EBITDA attributable to unverified power capacity is included in the valuation model until the underlying capacity is sufficiently evidenced.

Primary Source Provenance & Official References
[1] Ministry of Energy and Mineral Resources (ESDM) / PLN

RUPTL PLN 2025–2034 — electricity supply planning, grid development, and data-center demand context.

Official ESDM JDIH →
[2] Ministry of Agrarian Affairs and Spatial Planning (ATR/BPN)

Basic Agrarian Law (Law No. 5/1960) & Hak Guna Bangunan (HGB) Title Registration Rules.

Official ATR/BPN JDIH →